Railyard Dog Park Update: As of June 21st, the general excavation of the site and the deep caisson supports for the light poles have been completed. The percolation trenches will be excavated and completed by Thursday, June 24th. Additionally, the import of clean dirt and the sand/gravel play area will be completed next week in conjunction with the irrigation system. The week of July 5th Colorado Hardscapes will be forming and pouring the concrete curbs throughout the site which defines the dog park shape and function. Although progress is being made, the Railyard Dog Park still needs your support. Please visit http://www.railyarddogs.org to donate today! http://blog.riverfrontpark.com/index.php/1172/